Under ConstructionMahaRERA: P51900002151Truth Score™ 88/100 (Grade A+)
AJMERA CLASSIQUE
MahaRERA Verified Project

Configurations

2 BHK, 2.5 BHK, 3 BHK

Layout options

Possession

2023-12

Target completion

RERA Carpet Area

742 – 1077 sq.ft

Sanctioned carpet

Inventory Status

0/11 Units Sold (0%)

11 units available

88Grade A+

4-Pillar Statutory Truth Audit

Multi-Axis Radar

Exceptional Credibility · Low Delay Risk · Clean Legal Title

This Project
MMR Benchmark (70)
Legal & Title Cleanliness (22/25)Timeline Honesty (25/25)Construction Velocity (25/25)Financial & Escrow Health (16/25)

Pillar-by-Pillar Verification

Legal & Title Cleanliness22 / 25 pts
Performance: 88% of statutory ceilingSuperior Protection
Timeline Honesty25 / 25 pts
Performance: 100% of statutory ceilingSuperior Protection
Construction Velocity25 / 25 pts
Performance: 100% of statutory ceilingSuperior Protection
Financial & Escrow Health16 / 25 pts
Performance: 64% of statutory ceilingStandard Compliance
Statutory Buyer Negotiation Levers

11 unsold units remaining in the project. High leverage for parking/floor-rise waiver.

Verified Green Flags (7)
  • ✓Zero project completion extensions on government record.
  • ✓Completed and signed off as per target 2023-12-30.
  • ✓High construction pace: Average milestone completion is 100.0%.
  • ✓Certified Advocate Legal Title Report filed.
  • ✓Municipal Commencement Certificate (CC / IOD) verified.
Noted Statutory Caveats (1)
  • !High vacancy risk: Only 0% of inventory absorbed.
Statutory Buyer Due Diligence Dossier

Instant statutory audit with advocate title verification, Section 4 escrow bank account, and litigation history.

Download Audit Report (PDF)

Statutory Legal Title & Litigation Audit

Mandatory disclosures under Section 4(2)(l) of Real Estate (Regulation and Development) Act.

Clean Legal Record (Zero Litigations)

Clean Legal Title Disclosed

Zero pending suits, encumbrances, or court proceedings have been filed against AJMERA CLASSIQUE under MahaRERA Section 4(2)(l). Title certificate verified by accredited legal advocate.

Promoter Legal Entity

Statutory corporate identity under Companies Act / LLP Act.

Legal Name:JASMIN KISHORECHANDRA AJMERA
Organization Type:Individual
Registered Office:

F.P NO 1066

Section 4(2)(l)(D) Escrow Account

70% buyer receivables held in designated trust account.

Designated Bank:HDFC BANK
Branch IFSC:HDFC0000143
Account Status: Active RERA Escrow
Branch Address:

HDFC BANK CRAWFORD MARKET BRANCH NR GT HOSPITAL MARINE LINES

MahaRERA Audited Inventory Disclosures

Interactive Unit & Floor Stacking Plan

Inspect real-time booked vs available statutory units, exact RERA carpet areas, and floor placements directly reported by the promoter.

Available Unit
RERA Booked
Total Sanctioned Units

11

Statutory layout capacity
Available for Booking

11

Immediate inventory
Officially Booked

0

Agreements registered
Absorption Velocity

0%

06F
05F
04F
03F
02F
01F

Inventory Absorption & Sales Velocity

MahaRERA Audited

Real statutory unit booking progress registered in public government filings.

Booked (0)
Available (11)
0%Units Sold0 of 11

11 Units Remaining For Selection

Absorption Velocity: Early Booking Phase

Configuration-wise Absorption

3 BHK· ~1077 sq.ft
0/9 sold0%
Available: 9 unitsLeverage: Fast Depleting
2.5 BHK· ~874 sq.ft
0/1 sold0%
Available: 1 unitsLeverage: Fast Depleting
2 BHK· ~742 sq.ft
0/1 sold0%
Available: 1 unitsLeverage: Fast Depleting

Direct Government Data Advantage:Unlike developer sales brochures that often report artificial scarcity ("90% sold out"), this graph shows verified unit allocations registered under MahaRERA statutory Section 4 disclosures.

80%Physical

Physical Milestone Timeline (S-Curve)

Active Construction

Target Possession: 2023-12 · Verified statutory engineer progress.

Cumulative Earned Value Progress (EVM)
Actual Pace (80%)
Planned S-Curve
0%25%50%75%100%Foundation & PlinthMid-Tower SlabsPlaster & MEPStatutory OC / Possession

Pace on Track · Target Timeline Intact

Physical progress is weighted scientifically using civil engineering ratios: Substructure (15%), Superstructure (35%), Envelope & Finishing (30%), and MEP / Final OC (20%).

Physical Construction Activity Breakdown

Statutory stage-wise engineering completion filed under Section 4(2)(l)(D).

Overall Velocity:80%

Excavation

100%
Phase Status:Completed

Basement

100%
Phase Status:Completed

Podiums

100%
Phase Status:Completed

Plinth

100%
Phase Status:Completed

Super Structure Slabs

100%
Phase Status:Completed

Internal Walls & Plaster

100%
Phase Status:Completed

Sanitary Fittings

100%
Phase Status:Completed

Staircases & Lifts

100%
Phase Status:Completed

External Plumbing & Water Proofing

0%
Phase Status:Scheduled

Common Amenities

0%
Phase Status:Scheduled

Sanctioned Towers & Delivery Targets

Official building wings sanctioned by planning authorities.

Tower 11 Wing

AJMERA CLASSIQUE

Target Delivery: 2023-12-30

About the Project

AJMERA CLASSIQUE by Jasmin Kishorechandra Ajmera is an official statutory MAHARASHTRA RERA registered development (P51900002151). Exceptional Credibility · Low Delay Risk · Clean Legal Title.

Amenities & Infrastructure

Water conservation/rain water harvesting/recharge of ground waterGymFire protection and fire safety requirementsClub HouseLiftsIndoor Sports facilitySwimming PoolInternal Roads & Footpaths

Floor Plans & Sanctioned Blueprints

Official municipal sanctioned layout drawings filed with MahaRERA.

2.5 BHK874 sq.ft (81.22 sq.m)
Sanctioned BlueprintSheet 2.pdf
2BHK741 sq.ft (68.92 sq.m)
Sanctioned BlueprintSheet 2.pdf
3 BHK1,076 sq.ft (100.03 sq.m)
Sanctioned BlueprintSheet 2.pdf

RERA Statutory Document Vault

21 authentic public government disclosures filed under Section 4.

Sheet 2.pdf

Sanctioned Building / Layout Plan

IOD.pdf

Sanctioned Building / Layout Plan

31122018 Status of Work.pdf

Other

09072018 Status of Project.pdf

Other

FORM-B.pdf

Declaration Form B

12102018 Status of Work.pdf

Other

FORM - 2.pdf

Engineer Certificate (Form 2)

FORM - 4 Arch Certificate.pdf

Other

Ajmera Classique.pdf

Other

Legal Report.pdf

Legal Title report

Sheet 1.pdf

Sanctioned Building / Layout Plan

FORM - 3.pdf

Form - 3

09102019 Ltr to Rera for Status of project.pdf

Other

FORM - 1.pdf

Architect Certificate (Form 1)

Sheet 3.pdf

Sanctioned Building / Layout Plan

Pan Card.pdf

PAN Card

Ajmera Classique Status of Work.pdf

Other

FORM - 4 Arch Certificate.pdf

Other

Sheet 1.pdf

Sheet 1

Status of Project.pdf

Other

28032019 Status of Work.pdf

Other

Explore 3D

Fly the locality in photoreal 3D

Orbit the building, explore nearby context, then enter a floor.

Loading 3D locality…

Location & Connectivity

Mumbai City, Mumbai City, MAHARASHTRA

Open in Google Maps

Mumbai City Micro-Market Capital Trend

+43% 5-Yr Growth

Registered transaction rate per sq.ft based on statutory title deeds and micro-market filings.

2026 Registered Rate

₹7,200 / sq.ft

202120222023202420252026

5-Yr Capital Gain

+43%

~7.6% Annualized CAGR

Gross Rental Yield

3.7%

~₹22/sq.ft monthly rental

Infrastructure Driver

Mumbai City

High Growth Corridor · Highway & Railway Connectivity

Official Statutory Pricing

Price on Request

Government filings verify 11 unsold units remaining in this development.

Designated Escrow Bank

HDFC BANK

Active
IFSC Code:HDFC0000143
Branch:

HDFC BANK CRAWFORD MARKET BRANCH NR GT HOSPITAL MARINE LINES

Section 4(2)(l)(D) compliant: 70% of buyer payments are legally ring-fenced for this project only.

Explore More & Related Links

Deep-dive into verified statutory data, developer portfolios, and neighborhood projects.

View Full JASMIN KISHORECHANDRA AJMERA Profile→