Under ConstructionMahaRERA: P51900002871Truth Score™ 82/100 (Grade A+)
CHANDAN PRIDE
MahaRERA Verified Project

Configurations

Residential Flats

Layout options

Possession

2024-06

Target completion

RERA Carpet Area

Approved Sanctioned Plan

Statutory layout

Avg. Rate

₹ 37,455 / sq.ft (Govt Circle Rate)

Indicative price

82Grade A+

4-Pillar Statutory Truth Audit

Multi-Axis Radar

Exceptional Credibility · Low Delay Risk · Clean Legal Title

This Project
MMR Benchmark (70)
Legal & Title Cleanliness (25/25)Timeline Honesty (17/25)Construction Velocity (20/25)Financial & Escrow Health (20/25)

Pillar-by-Pillar Verification

Legal & Title Cleanliness25 / 25 pts
Performance: 100% of statutory ceilingSuperior Protection
Timeline Honesty17 / 25 pts
Performance: 68% of statutory ceilingStandard Compliance
Construction Velocity20 / 25 pts
Performance: 80% of statutory ceilingSuperior Protection
Financial & Escrow Health20 / 25 pts
Performance: 80% of statutory ceilingSuperior Protection
Verified Green Flags (7)
  • ✓Completed and signed off as per target 2024-06-30.
  • ✓Active construction pace: 80.5% physical completion.
  • ✓Certified Advocate Legal Title Report filed.
  • ✓Municipal Commencement Certificate (CC / IOD) verified.
  • ✓Sanctioned building layout plan approved by municipal authority.
Noted Statutory Caveats (1)
  • !Statutory project extension certificate applied with MahaRERA.
Statutory Buyer Due Diligence Dossier

Instant statutory audit with advocate title verification, Section 4 escrow bank account, and litigation history.

Download Audit Report (PDF)

Statutory Legal Title & Litigation Audit

Mandatory disclosures under Section 4(2)(l) of Real Estate (Regulation and Development) Act.

Clean Legal Record (Zero Litigations)

Clean Legal Title Disclosed

Zero pending suits, encumbrances, or court proceedings have been filed against CHANDAN PRIDE under MahaRERA Section 4(2)(l). Title certificate verified by accredited legal advocate.

Promoter Legal Entity

Statutory corporate identity under Companies Act / LLP Act.

Legal Name:SANGHVI LAND DEVELOPERS PVT LTD
Organization Type:Company
Registered Office:

189PART

Section 4(2)(l)(D) Escrow Account

70% buyer receivables held in designated trust account.

Designated Bank:AXIS BANK
Branch IFSC:UTIB0000029
Account Status: Active RERA Escrow
Branch Address:

SAI HERITAGE, TIALK ROAD, NEAR BALAJI MANDIR, GHATKOPAR EAST, MUMBAI -400077

76%Physical

Physical Milestone Timeline (S-Curve)

Active Construction

Target Possession: 2024-06 · Verified statutory engineer progress.

Cumulative Earned Value Progress (EVM)
Actual Pace (76%)
Planned S-Curve
0%25%50%75%100%Foundation & PlinthMid-Tower SlabsPlaster & MEPStatutory OC / Possession

Pace on Track · Target Timeline Intact

Physical progress is weighted scientifically using civil engineering ratios: Substructure (15%), Superstructure (35%), Envelope & Finishing (30%), and MEP / Final OC (20%).

Physical Construction Activity Breakdown

Statutory stage-wise engineering completion filed under Section 4(2)(l)(D).

Overall Velocity:70%

Excavation

100%
Phase Status:Completed

Basement

100%
Phase Status:Completed

Podiums

0%
Phase Status:Scheduled

Plinth

100%
Phase Status:Completed

Super Structure Slabs

100%
Phase Status:Completed

Internal Walls & Plaster

100%
Phase Status:Completed

Sanitary Fittings

100%
Phase Status:Completed

Staircases & Lifts

100%
Phase Status:Completed

External Plumbing & Water Proofing

0%
Phase Status:Scheduled

Common Amenities

0%
Phase Status:Scheduled

Sanctioned Towers & Delivery Targets

Official building wings sanctioned by planning authorities.

Tower 11 Wing

CHANDAN PRIDE

Target Delivery: 2024-06-30

About the Project

CHANDAN PRIDE by Sanghvi Land Developers is an official statutory MAHARASHTRA RERA registered development (P51900002871). Exceptional Credibility · Low Delay Risk · Clean Legal Title.

Amenities & Infrastructure

Water conservation/rain water harvesting/recharge of ground waterGymFire protection and fire safety requirementsClub HouseLiftsIndoor Sports facilitySwimming PoolInternal Roads & Footpaths

RERA Statutory Document Vault

11 authentic public government disclosures filed under Section 4.

Chandan Pride Title Certificate 060717.pdf

Legal Title report

FORM 2 (1).pdf

Engineer Certificate (Form 2)

Chandan Pride IOD 060717.pdf

Sanctioned Building / Layout Plan

FORM B.pdf

Declaration Form B

Chandan Pride Approval Plan Letter 060717.pdf

Sanctioned Building / Layout Plan

DEEPAK SHAH - Archtech Certificate.pdf

Architect Certificate (Form 1)

ENGINEER CERTIFICATE.pdf

Engineer Certificate (Form 2)

CA certificate.pdf

CA Certificate (Form 3)

SLD Pan Card 060717.pdf

PAN Card

SLD Chandan Pride Form B Affidavit Cum Declaration 250717.pdf

Declaration Form B

form 1.pdf

Architect Certificate (Form 1)

Location & Connectivity

Mumbai City, Mumbai City, MAHARASHTRA

Open in Google Maps
Official Statutory Pricing

Price on Request

Verified MahaRERA price sheets, floor-rise schedules, and tax breakdowns on statutory record.

Designated Escrow Bank

AXIS BANK

Active
IFSC Code:UTIB0000029
Branch:

SAI HERITAGE, TIALK ROAD, NEAR BALAJI MANDIR, GHATKOPAR EAST, MUMBAI -400077

Section 4(2)(l)(D) compliant: 70% of buyer payments are legally ring-fenced for this project only.

Explore More & Related Links

Deep-dive into verified statutory data, developer portfolios, and neighborhood projects.

View Full SANGHVI LAND DEVELOPERS PVT LTD Profile→