Under ConstructionMahaRERA: P51700001031Truth Score™ 76/100 (Grade A)

LODHA AMARA - TOWER 26, 27, 28, 30, 34, 35

LODHA AMARA - TOWER 26, 27, 28, 30, 34, 35
MahaRERA Verified Project

Configurations

1 BHK, 2 BHK, 3 BHK

Layout options

Possession

2021-12

Target completion

RERA Carpet Area

366 – 1260 sq.ft

Sanctioned carpet

Inventory Status

942/959 Units Sold (98%)

17 units available

76Grade A

4-Pillar Statutory Truth Audit

Multi-Axis Radar

High Credibility · Low to Moderate Risk · Statutory Approvals Intact

This Project
MMR Benchmark (70)
Legal & Title Cleanliness (6/25)Timeline Honesty (25/25)Construction Velocity (20/25)Financial & Escrow Health (25/25)

Pillar-by-Pillar Verification

Legal & Title Cleanliness6 / 25 pts
Performance: 24% of statutory ceilingAction Required
Timeline Honesty25 / 25 pts
Performance: 100% of statutory ceilingSuperior Protection
Construction Velocity20 / 25 pts
Performance: 80% of statutory ceilingSuperior Protection
Financial & Escrow Health25 / 25 pts
Performance: 100% of statutory ceilingSuperior Protection
Statutory Buyer Negotiation Levers

17 unsold units remaining in the project. High leverage for parking/floor-rise waiver.

Verified Green Flags (7)
  • ✓Zero project completion extensions on government record.
  • ✓Completed and signed off as per target 2021-12-30.
  • ✓Active construction pace: 81.8% physical completion.
  • ✓Certified Advocate Legal Title Report filed.
  • ✓Sanctioned building layout plan approved by municipal authority.
Noted Statutory Caveats (2)
  • !Commencement Certificate (CC) document missing or pending.
  • !CRITICAL: Active interim stay / injunction order passed against project!
Statutory Buyer Due Diligence Dossier

Instant statutory audit with advocate title verification, Section 4 escrow bank account, and litigation history.

Download Audit Report (PDF)

Statutory Legal Title & Litigation Audit

Mandatory disclosures under Section 4(2)(l) of Real Estate (Regulation and Development) Act.

⚠ Active Interim Injunction / Stay

Critical Legal Caution: Stay Order Passed

An interim preventive injunction or stay order has been registered on judicial record for this project. Buyers should seek formal legal counsel before executing sale deeds.

Court NameCase Number & YearTypeInjunction / StayDetails
Bombay High Court1737 (2016)Civil Petition Stay Passed—
Bombay High Court290 (2016)Civil Petition Stay Passed—

Promoter Legal Entity

Statutory corporate identity under Companies Act / LLP Act.

Legal Name:MACROTECH DEVELOPERS LIMITED
Organization Type:Company
Registered Office:

Block-C, WTT, C.S No. 8pt. SaltPan Division., ., .

Section 4(2)(l)(D) Escrow Account

70% buyer receivables held in designated trust account.

Designated Bank:UNION BANK OF INDIA
Branch IFSC:UBIN0549584
Account Status: Active RERA Escrow
Branch Address:

Union Bank Bhavan, Nariman point , Mumbai-400021

MahaRERA Audited Inventory Disclosures

Interactive Unit & Floor Stacking Plan

Inspect real-time booked vs available statutory units, exact RERA carpet areas, and floor placements directly reported by the promoter.

Available Unit
RERA Booked
Total Sanctioned Units

959

Statutory layout capacity
Available for Booking

17

Immediate inventory
Officially Booked

942

Agreements registered
Absorption Velocity

98%

28F
27F
26F
25F
24F
23F
22F
21F
20F
19F
18F
17F
16F
15F
14F
13F
12F
11F
10F
09F
08F
07F
06F
05F
04F
03F
02F
01F

Inventory Absorption & Sales Velocity

MahaRERA Audited

Real statutory unit booking progress registered in public government filings.

Booked (942)
Available (17)
98%Units Sold942 of 959

17 Units Remaining For Selection

Absorption Velocity: High Demand

Configuration-wise Absorption

2 BHK· ~585 sq.ft
719/730 sold98%
Available: 11 unitsLeverage: High Choice / Negotiable
1 BHK· ~436 sq.ft
151/156 sold97%
Available: 5 unitsLeverage: Fast Depleting
3 BHK· ~1018 sq.ft
61/62 sold98%
Available: 1 unitsLeverage: Fast Depleting
4 BHK· ~1086 sq.ft
5/5 sold100%
Available: 0 unitsLeverage: Fast Depleting
5BHKJODI· ~1259 sq.ft
4/4 sold100%
Available: 0 unitsLeverage: Fast Depleting
5BHK JODI· ~1256 sq.ft
2/2 sold100%
Available: 0 unitsLeverage: Fast Depleting

Direct Government Data Advantage:Unlike developer sales brochures that often report artificial scarcity ("90% sold out"), this graph shows verified unit allocations registered under MahaRERA statutory Section 4 disclosures.

76%Physical

Physical Milestone Timeline (S-Curve)

Active Construction

Target Possession: 2021-12 · Verified statutory engineer progress.

Cumulative Earned Value Progress (EVM)
Actual Pace (76%)
Planned S-Curve
0%25%50%75%100%Foundation & PlinthMid-Tower SlabsPlaster & MEPStatutory OC / Possession

Pace on Track · Target Timeline Intact

Physical progress is weighted scientifically using civil engineering ratios: Substructure (15%), Superstructure (35%), Envelope & Finishing (30%), and MEP / Final OC (20%).

Physical Construction Activity Breakdown

Statutory stage-wise engineering completion filed under Section 4(2)(l)(D).

Overall Velocity:70%

Excavation

100%
Phase Status:Completed

Basement

100%
Phase Status:Completed

Podiums

0%
Phase Status:Scheduled

Plinth

100%
Phase Status:Completed

Super Structure Slabs

100%
Phase Status:Completed

Internal Walls & Plaster

100%
Phase Status:Completed

Sanitary Fittings

100%
Phase Status:Completed

Staircases & Lifts

100%
Phase Status:Completed

External Plumbing & Water Proofing

0%
Phase Status:Scheduled

Common Amenities

0%
Phase Status:Scheduled

Sanctioned Towers & Delivery Targets

Official building wings sanctioned by planning authorities.

Tower 11 Wing

TOWER -26

Target Delivery: 2021-12-30

Tower 21 Wing

TOWER -27

Target Delivery: 2021-12-30

Tower 31 Wing

TOWER -28

Target Delivery: 2021-12-30

Tower 41 Wing

TOWER -30

Target Delivery: 2021-12-30

Tower 51 Wing

TOWER -34

Target Delivery: 2021-12-30

Tower 61 Wing

TOWER- 35

Target Delivery: 2021-12-30

About the Project

LODHA AMARA - TOWER 26, 27, 28, 30, 34, 35 by Macrotech Developers is an official statutory MAHARASHTRA RERA registered development (P51700001031). High Credibility · Low to Moderate Risk · Statutory Approvals Intact.

Amenities & Infrastructure

Water conservation/rain water harvesting/recharge of ground waterGymFire protection and fire safety requirementsClub HouseLiftsIndoor Sports facilitySwimming PoolInternal Roads & Footpaths

Floor Plans & Sanctioned Blueprints

Official municipal sanctioned layout drawings filed with MahaRERA.

1 BHK C366 sq.ft (34.02 sq.m)
Sanctioned BlueprintLAYOUT DATED - 12-4-2017-26,27,28,30,34,35.pdf
1 BHK D500 sq.ft (46.5 sq.m)
Sanctioned BlueprintLAYOUT DATED - 12-4-2017-26,27,28,30,34,35.pdf
1BHK435 sq.ft (40.5 sq.m)
Sanctioned BlueprintLAYOUT DATED - 12-4-2017-26,27,28,30,34,35.pdf
1BHK472 sq.ft (43.86 sq.m)
Sanctioned BlueprintLAYOUT DATED - 12-4-2017-26,27,28,30,34,35.pdf
1BHK457 sq.ft (42.47 sq.m)
Sanctioned BlueprintLAYOUT DATED - 12-4-2017-26,27,28,30,34,35.pdf
1BHK366 sq.ft (34.02 sq.m)
Sanctioned BlueprintLAYOUT DATED - 12-4-2017-26,27,28,30,34,35.pdf

RERA Statutory Document Vault

24 authentic public government disclosures filed under Section 4.

W 27R (R).pdf

Sanctioned Building / Layout Plan

W 27R A (R).pdf

Sanctioned Building / Layout Plan

W 34 (R).pdf

Sanctioned Building / Layout Plan

W 34AA (R) Reduced.pdf

Sanctioned Building / Layout Plan

W 34BB (R) Reduced.pdf

Sanctioned Building / Layout Plan

W 35_1_ (R) Reduced.pdf

Sanctioned Building / Layout Plan

W 28A (R).pdf

Sanctioned Building / Layout Plan

W 30 (R).pdf

Sanctioned Building / Layout Plan

W 35AA (R) Reduced.pdf

Sanctioned Building / Layout Plan

LODHA DEVELOPERS THANE PVT LTD PAN CARD.pdf

PAN Card

LDL to MDL.pdf

Other

Lodha Amara 26,27,28,30,34,35.pdf

Engineer Certificate (Form 2)

W 27R B (R).pdf

Sanctioned Building / Layout Plan

W 28 (R).pdf

Sanctioned Building / Layout Plan

W 26R (R).pdf

Sanctioned Building / Layout Plan

W 30A(R).pdf

Sanctioned Building / Layout Plan

LAYOUT DATED - 12-4-2017-26,27,28,30,34,35.pdf

Layout Dated - 12-4-2017-26,27,28,30,34,35

W 26R, W 28, W 30 (R).pdf

Sanctioned Building / Layout Plan

Amara all TR merged.pdf

Legal Title report

Lodha Amara Tower 26 27 28 30 34 35.pdf

Architect Certificate (Form 1)

Title Report.pdf

Legal Title report

T 26 to 28 30 34 35.pdf

T 26 To 28 30 34 35

W 35BB (R) Reduced.pdf

Sanctioned Building / Layout Plan

Amara Tower 27 28 30 34 35.pdf

Declaration Form B

Explore 3D

Fly the locality in photoreal 3D

Orbit the building, explore nearby context, then enter a floor.

Loading 3D locality…

Location & Connectivity

Thane, Thane, MAHARASHTRA

Open in Google Maps

Thane City / Majiwada Micro-Market Capital Trend

+43% 5-Yr Growth

Registered transaction rate per sq.ft based on statutory title deeds and micro-market filings.

2026 Registered Rate

₹14,500 / sq.ft

202120222023202420252026

5-Yr Capital Gain

+43%

~7.6% Annualized CAGR

Gross Rental Yield

3.5%

~₹42/sq.ft monthly rental

Infrastructure Driver

Thane City / Majiwada

Thane-Borivali Twin Tunnel (15-min link) + Metro Line 4 & 5 Corridors

Official Statutory Pricing

Price on Request

Government filings verify 17 unsold units remaining in this development.

Designated Escrow Bank

UNION BANK OF INDIA

Active
IFSC Code:UBIN0549584
Branch:

Union Bank Bhavan, Nariman point , Mumbai-400021

Section 4(2)(l)(D) compliant: 70% of buyer payments are legally ring-fenced for this project only.

Explore More & Related Links

Deep-dive into verified statutory data, developer portfolios, and neighborhood projects.

View Full MACROTECH DEVELOPERS LIMITED Profile→